Lock floor

The heavy bamboo lock buckle flooring is easy to install and disassemble, making it the preferred choice for the DIY family, which can save you a large amount of installation costs.
It has been precision processed using patented locking technology and internationally advanced floor processing equipment. Simply follow the instructions and assemble them one by one, making it easy for you to lay a perfectly seamless and aesthetically pleasing floor.


In order to match our flooring, we provide a complete set of flooring accessories, including outer corner (trapezoidal nose) reduction panels for stairs and quarter round edges. These components are all produced from heavy bamboo and have the same quality and characteristics as the flooring, and come in the following shapes. (Customized for customers while meeting the minimum order quantity)

  • Simplified board
    Specifications:
    1850mm*45mm*12mm
    Structure: Heavy Bamboo
    Color: Carbonized/Natural
  • Simplified board
    Specifications:1850mm*45mm*12mm
    Structure: Heavy Bamboo
    Color: Carbonized/Natural
  • Simplified board
    Specifications:1850mm*45mm*12mm
    Structure: Heavy Bamboo
    Color: Carbonized/Natural
  • Simplified board
    Specifications:1850mm*45mm*12mm
    Structure: Heavy Bamboo
    Color: Carbonized/Natural
  • Simplified board
    Specifications:1850mm*45mm*12mm
    Structure: Heavy Bamboo
    Color: Carbonized/Natural
  • Simplified board
    Specifications:1850mm*45mm*12mm
    Structure: Heavy Bamboo
    Color: Carbonized/Natural
Decking
  • 1. Fix the keel to the ground with screws.
  • 2. Pave a floor onto the keel, and then push a fastener above each keel into the cherry blossom groove.
  • 3. Clip the second floor slot into the other side of the fastener.
  • 4. Connect each fastener to the keel with wooden screws to secure the floor, and so on.
Floor flatness requirements
Measure the ground with a 2m guiding rule, and the height of the garbage between the guiding rule and the ground should be ≤ 5mm
Ground moisture content
No more than 20%, and rectification should be carried out if it exceeds the limit.
Keel
Keel thickness: ≥ 20mm, width: ≥ 35mm
Sub floor (optional for use)
Thickness ≥ 9mm, using multi-layer plywood, blockboard, and particle board
Anti lake cloth
The moisture-proof interface should be tightly glued, and the interface should be overlapped by more than 20cm, and the wall corners should be turned up 5cm
Clearance between floor and wall
8-12mm
Floor eye-catching angle
An angle of 30 ° -50 ° from the horizontal
Requirements for pavement width and length limitations
The laying length in the width direction of the floor is ≤ 6m, and the length of the floor is set to be $10m. In order to meet the above requirements, a winding system should be set up in appropriate positions and decorated with cloth strips.
Floor flatness requirements
Measure the ground with a 2m guiding rule, and the height of the garbage between the guiding rule and the ground should be ≤ 5mm
Ground moisture content
No more than 20%, and rectification should be carried out if it exceeds the limit.
Anti lake cloth
The moisture-proof interface should be tightly glued, and the interface should be overlapped by more than 20cm, and the wall corners should be turned up 5cm
Clearance between floor and wall
8-12mm
Requirements for pavement width and length limitations